Project Title:
Electrical Distribution System Upgrades - Phase 1
Client:
Johns Hopkins University Applied Physics Laboratory
Location:
Laurel, MD
Summary:
The Johns Hopkins University (JHU) Applied Physics Lab (APL)
consists of 1.8 million GSF of laboratory, manufacturing / research, and office
space. Several near term facilities are planned for the campus through the year
2006 to increase the campus to 2.4 million GSF of building space. The ultimate
projected growth will increase the campus building to 3.9 million GSF beyond the
year 2010.
Ross Infrastructure provided the master planning of the electrical system which
included evaluation of the existing 33 kV distribution system serving the APL
campus and generating various options to improve the reliability and redundancy
of the electrical distribution system, identify budgetary construction costs for
each option, establish the criteria for the future campus electrical
distribution as well as to provide direction to support near term facilities
planned for construction. The overall budget estimated for the complete
build-out of the electrical distribution system was $5,000,000.
The construction project to implement the master plan recommendations is
identified as the Electrical Distribution System Upgrades (EDSU). Phase 1 of the
EDSU project involved the transition of approximately 60% (2,000 LF) of overhead
33 kV overhead cabling to underground encased conduits. This required
approximately 7,000 LF of underground ductbanks to be installed
throughout the
campus.
The existing 33 kV radial distribution system was replace and Phase 1 began the
implementation of the new primary loop and tap distribution to the individual
buildings. The new loop and tap
system provides 33 kV cabling redundancy while the underground distribution
improves the system's reliability as well as to improve the aesthetics of the
campus.
Additional goals for the Phase 1 project involved the replacement of an obsolete
and undersized 33 kV to 480 volts secondary substation which served multiple
local buildings. Phase 1 also
included the extension of ther existing telecommunications system. The budget
for Phase 1 was $1,800,000.